Heineken Biomass Plant

Home/Manufacturing & Industrial/Heineken Biomass Plant
Heineken Biomass Plant 2015-12-18T11:54:34+00:00

Project Description

Scottish and Newcastle – John Smiths Brewery

  • Project: Biomass Plant
  • Location: Tadcaster
  • Value: £1.6m

Carry out various works in stages to super structure of new biomass plant. First phase demolition & site set up incl full time site supervisor dedicated facilities, health & safety etc. Second phase excavation & formwork, drainage, structural steel, crane age & wall cladding, pipe bridges incl high level scaffolds & working platforms. Phase 3 lighting, aluminium doors, fire protection & finishes. All over an approximate 8 month period.